Main menu

  • Street level view of Phelps and Newcomb intersection
  • Street level view of Corbett and Clayton intersection

Various Locations Pavement Renovation and Sewer Replacement No. 59

San Francisco Public Works has contracted with Michael O’Shaughnessy Construction Inc. to install new sewer utilities and renovate the roadway at various locations in San Francisco as part of the Various Locations Pavement Renovation and Sewer Replacement Project No. 59 (VL59). We will be performing this work in the Central Bayview, Twin Peaks, Eureka Valley and Duboce Park neighborhoods. 

We have inspected the sewer facilities of all the blocks listed below, and will be replacing those that we found to be cracked and/or broken.  Replacing these pipes now will prevent possible collapse of the sewer mains and pavement in the future. Sewer service will not be interrupted during the construction.  Pavement Renovation and Sewer replacement work will occur between September 2023 and September 2024.

This project will include sewer main replacement, curb ramp installation, street base repairs and repaving. Work hours will vary by location, however, typical working hours are 7 a.m. to 5 p.m. Monday through Friday. Weekend work is allowed but has not been scheduled at this time.

Street resurfacing work will be taking place on the following blocks. Only those in bold will be receiving sewer work as well:

Phelps Street from Newcomb to La Salle - In progress

Phelps Street from La Salle to Fairfax

McKinnon Avenue from Phelps to 3rd - In progress

Oakdale Avenue from Phelps to Newhall - In progress

Oakdale Avenue from Newhall to 3rd 

Quint Street from Oakdale to Newcomb

Underwood Avenue from Jennings to Ingalls - Sewer Work Starting 4/29

Shafter Avenue from Industrial to end

Burnett Avenue from Twin Peaks to Hopkins

Burnett Avenue from Danview to Crestline

Graystone Terrace from Iron Alley to Corbett

Corbett Avenue from Clayton to Mars - Complete

Douglass Street from 21st to 22nd - Complete

19th Street from Yukon to Douglass - Complete

19th Street from Collingwood to Castro - Complete

Collingwood Street from 18th to 19th - Complete

15th Street from Market to Church - Complete - Complete

States Street from Levant to Castro - Complete

Levant Street from States to Lower Terrace - Complete

Ord Street from Ord Court to Saturn Street Stairway - Complete

Ord Street from Saturn Street Stairway to 17th - Complete

Ord Street from 17th to Corbett - Complete

Construction Updates

4/24/24: On Monday, April 29th, we will begin sewer main replacement work on Underwood Avenue between Jennings Street and Ingalls Street. Once we install the sewer main on this block, we will then replace any damaged sewer laterals, which are the smaller pipes that run perpendicular to the curb and connect the sewer main with household plumbing systems. We expect this work to take about 3 to 4 weeks to complete, barring any unforeseen circumstances.After work on this block is complete, we will then re-pave the entire block. Note: this work will not interrupt plumbing service, and you can continue to use your household plumbing normally throughout this project. During construction, all on-street parking and through traffic will be prohibited on this block. Local access to residents of Underwood Avenue will remain throughout the project.

4/2/24: On Monday, April 8th through Wednesday, April 10th, we will be re-paving Douglass Street, 19th Street and Corbett Avenue. Work will progress as follows:

Monday 4/8: Grind and re-pave Douglass Street from 21st Street to 22nd Street. Grind 19th Street from Yukon Street to Douglass Street.

Tuesday 4/9: Re-pave 19th Street from Yukon Street to Douglass Street. Grind Corbett Avenue from Mars Street to Clayton Street.

Wednesday 4/10: Re-pave Corbett Avenue from Mars Street to Clayton Street. 

3/25/24: On Monday, April 1st and Tuesday, April 2nd, 19th Street between Collingwood and Castro as well as Collingwood Street between 18th and 19th Streets will be re-paved. The first step of this work is to grind away the existing asphalt roadway surface, which will take place on Monday, April 1st. Then, we will re-apply 2 new inches of asphalt to the roadway on Tuesday, April 2nd. This work should take roughly two full workdays to complete barring any unforeseen circumstances or inclement weather.

3/11/24: On Monday, March 18th, we will begin working on 19th Street between Collingwood and Castro, as well as Collingwood Street between 18th and 19th Streets. The first step of this work will be some spot repairs to the sewer main on Collingwood between 18th and 19th, specifically in front of 157, 163 and 195 Collingwood Street, Once this sewer work is complete, we will reconstruct the concrete street base on 19th Street between Collingwood and Castro. The final phase of this work will be to re-pave the entire area - 19th from Collingwood and Castro and Collingwood between 18th and 19th. In total, we expect this work to take 3 to 4 weeks to complete. Note: this work will not interrupt plumbing service, and you can continue to use your household plumbing normally throughout this project. During construction, all on-street parking and through traffic will be prohibited on this block. Local access to residents of the area will remain throughout the project.

3/11/24: On Monday, March 18th, we will begin sewer main replacement work on Oakdale Avenue between Phelps Street and 3rd Street. Once we install the sewer main on this block, we will then replace any damaged sewer laterals, which are the smaller pipes that run perpendicular to the curb and connect the sewer main with household plumbing systems. We expect this work to take about 3 to 4 weeks to complete, barring any unforeseen circumstances.After work on this block is complete, we will then re-pave the entire block. Note: this work will not interrupt plumbing service, and you can continue to use your household plumbing normally throughout this project. During construction, all on-street parking and through traffic will be prohibited on this block. Local access to residents of Oakdale Avenue will remain throughout the project.

2/29/24: On Monday, March 4th, we will begin sewer main replacement work on Phelps Street between Newcomb Avenue and La Salle Avenue . Once we install the sewer main on these blocks, we will then replace any damaged sewer laterals, which are the smaller pipes that run perpendicular to the curb and connect the sewer main with household plumbing systems. We expect this work to take about 2 to 3 weeks to complete, barring any unforeseen circumstances.After sewer work on this block is complete, we will then construct 12 new ADA-compliant curb ramps - 6 at the intersection of Phelps and La Salle, and another 6 at the intersection of Phelps and McKinnon. The final phase of this work will be to re-pave the entire two-block stretch of Phelps. In total, we expect this work to take 6 to 7 weeks to complete. Note: this work will not interrupt plumbing service, and you can continue to use your household plumbing normally throughout this project. During construction, all on-street parking and through traffic will be prohibited on this block. Local access to residents of Corbett Avenue will remain throughout the project.

2/28/24: On Monday, March 4th through Friday, March 8th, we will paving the following blocks: States Street from Levant Street to Castro Street, Ord Street from Ord Court to Corbett Street, 15th Street from Market Street to Church Street, and Levant Street from States Street to Lower Terrace. The Daily Schedule will be as follows: 

Monday, March 4th: Grind States Street from Levant Street intersection to 121 States Street, re-pave from Levant Street to 253 States Street.

Tuesday, March 5th: Re-pave States Street from 253 States Street to 121 States Street. Grind States Street from 121 States Street to Castro Street intersection.

Wednesday, March 6th: Re-pave States Street from 121 States Street to Castro Street intersection.

Wednesday, March 6th: Grind 15th Street from Market Street to Castro Street

Thursday, March 7th: Re-pave 15th Street from Market Street to Castro Street.

Friday, March 8th: Grind and re-pave Ord Street from Ord Court to Corbett Street.

Friday, March 8th: Grind and re-pave Levant Street from States Street to Lower Terrace.

UPDATE: Due to rainy weather, we must postpone paving work on States Street, Levant Street, Ord Street and 15th Street until further notice. It was initially scheduled to begin on February 1st.

1/23/24: Starting on Thursday, February 1st, our paving contractor will begin re-paving States Street from Levant to Castro, Levant Street from States to Lower Terrace, Ord Street from Ord Court to Corbett, and 15th Street from Market to Church. The first step of this work is to grind away the existing asphalt roadway surface. Then, we will re-apply 2 new inches of asphalt to the roadway. This work should take roughly two weeks to complete barring any unforeseen circumstances or inclement weather.

1/8/24: On Tuesday, January 16th, we will begin sewer main replacement work on Corbett Avenue between Mars Street and Clayton Street. Once we install the sewer main on this block, we will then replace any damaged sewer laterals, which are the smaller pipes that run perpendicular to the curb and connect the sewer main with household plumbing systems. We expect this work to take about 5 to 6 weeks to complete, barring any unforeseen circumstances.After work on this block is complete, we will then re-pave the entire block. Note: this work will not interrupt plumbing service, and you can continue to use your household plumbing normally throughout this project. During construction, all on-street parking and through traffic will be prohibited on this block. Local access to residents of Corbett Avenue will remain throughout the project.

On Friday, January 12th, we will begin constructing new, ADA-compliant curb ramps at two locations on Burnett Avenue - at Dixie Alley and at Glenview Drive. Work at both locations should take roughly to weeks to complete, barring any unforeseen circumstances. A few weeks after this work is complete, we will come back and re-pave all of Burnett Avenue from Twin Peaks Boulevard to Dawnview Way. Residents of this area will receive additional notice in the weeks leading up to this paving work.

11/27/23: On Monday, December 4th, we will begin sewer main replacement work on 19th Street between Douglass Street and Douglass Street. Once we install the sewer main on this block, we will then replace any damaged sewer laterals, which are the smaller pipes that run perpendicular to the curb and connect the sewer main with household plumbing systems. We expect this work to take about 5 to 6 weeks to complete, barring any unforeseen circumstances.After work on this block is complete, we will then re-pave the entire block. Note: this work will not interrupt plumbing service, and you can continue to use your household plumbing normally throughout this project. During construction, all on-street parking and through traffic will be prohibited on this block. Local access to residents of 19th Street will remain throughout the project.

11/27/23: On Monday, December 4th, we will begin constructing new, ADA-compliant curb ramps at the intersection of States Street and Levant Street. We will also be constructing curb ramps mid-block on States Street between Levant Street and Castro Street. We expect work at these two locations to take roughly one week to complete. Street and sidewalk access will be maintained at all times throughoug this project, but some street parking restrictions will be in place during construction. A few weeks after this work is complete, we will be re-paving the entire block of States Street from Levant Street to Castro Street.

11/17/23: On Monday, November 27th, we will begin sewer main replacement work on Ord Street between 17th Street and the Saturn Street Stairway. Once we install the sewer main on this block, we will then replace any damaged sewer laterals, which are the smaller pipes that run perpendicular to the curb and connect the sewer main with household plumbing systems. We expect this work to take about 2 to 3 weeks to complete, barring any unforeseen circumstances.After work on this block is complete, we will then re-pave the entire block. Note: this work will not interrupt plumbing service, and you can continue to use your household plumbing normally throughout this project. During construction, all on-street parking and through traffic will be prohibited on this block. Local access to residents of Ord Street will remain throughout the project.

On Monday, November 27th, we will begin curb ramp construction work at the intersection of Sharon Street and 15th Street. The scope of work for this project includes the construction of two new curb ramps across Sharon Street as well as the reconstruction of nearby portions of the sidewalk and curb lane. We expect this work to tke about two weeks to complete barring any unforeseen circumstances, equipment issues, or weather issues.

Pavement and Sewer Renovation
Location
Throughout the Bayview, Twin Peaks, Eureka Valley, Duboce Triangle and Corona Heights Neighborhoods
Start Summer, 2023
Completion Summer, 2024
Release Date
Thursday, August 24, 2023
Budget
$7.7 Million
Project Manager
Paul Barradas, (628) 271-2580
Project Team

San Francisco Public Works

Michael O'Shaughnessy Construction Inc.

Contact
Benjamin Peterson
Phone
(628) 271-3057