Main menu

  • Photo of intersection of Mission and Persia Streets
  • Mission Geneva Phase 1 Rendering
  • Mission Geneva Phase 2 Rendering
  • Mission Geneva Phase 3 Rendering
  • Mission Geneva Phase 4 Rendering

Mission Street and Geneva Avenue Infrastructure Improvement Project

Project Update (Late December 2023):

S.F. Public Works has completed grinding and paving operations on Geneva Avenue between Prague Street and Mission Street. In January, crews will return to Geneva Avenue to complete any remaining punch list work. Segement I of the project is close to being completed. 

Segment II (Mission Street: Geneva to Russia) is currently on pause due to the holiday moratorium. Crews will resume work on Segment II in January 2024. The contractor will resume electrical and concrete flatwork (curb ramp, bulb-out and bus pad work). As a gentle reminder, when the contractor frames and pours a new bus pad, the area will remain closed to ALL vehicle traffic for approximately 10 days. Although work at each bus pad is expected to only take a few days to complete, the area will remain closed in order for the concrete to cure and reach the necessary strength before suporting the weight of vehicles. During this time, any affected bus stops will be temporarily relocated. We apologize in advance for the 24x7 closure at bus pad/bus stop locations.  
 

Project Description:
San Francisco Public Works, the San Francisco Municipal Transportation Agency (SFMTA), and the San Francisco Public Utilities are partnering to bring safety improvements and infrastructure upgrades to the Excelsior and Outer Mission neighborhoods. The Mission Street and Geneva Avenue Infrastructure Improvement Project includes approximately forty sidewalk bulb-outs, upgraded traffic signals at twenty locations, sewer main replacement at ten locations, concrete street base replacement work and street repaving throughout the project area. The project limits are:

  • Geneva Avenue: Prague Street to Mission Street
  • Mission Street: Geneva Avenue to Highway 280 Overpass (Trumbull Street)
     

Mission Street and Geneva Avenue are part of San Francisco's Vision Zero High Injury Network - the 13% of city streets where 75% of the severe and fatal collisions occur. The City and County of San Francisco adopted Vision Zero as a policy in 2014, committing to build better and safer streets, educate the public on traffic safety, enforce traffic laws, and adopt policy changes that save lives. The goal is to create a culture that prioritizes traffic safety and to ensure that mistakes on our roadways don’t result in serious injuries or death. The result of this collaborative, citywide effort will be safer, more livable streets as we work to eliminate traffic fatalities.

Once construction starts, we'll be sending regular e-updates to inform neighbors about the current and upcoming scopes of work, possible impacts, weekend work, completed project milestones, etc. Neighbors interested in receiving e-updates could SIGN-UP HERE.

For additional information on this project, please visit https://www.sfmta.com/projects/mission-geneva-safety-project

Project Sequencing & Duration

The overall project duration is anticipated to be approximately 3 years. However, in order to minimize any impacts associated with construction, this project will be completed in segments. A completion timeline has been placed on each segment to minimize the time it is under construction. There will be an overlap in segments as work is completed in one segment and starts on the next one. The segments are as follows:
 
Segment I 
Geneva Avenue (Mission Street to Prague Street) 
(Approximately 11.5 months / November 2022 – November 2023)
 
Segment II 
Mission Street (Geneva Avenue to Russia Avenue)
(Approximately 10 months / September 2023 – June 2024)
 
Segment III
Mission Street (Russia Avenue to Theresa Street) 
(Approximately 11 months / May 2024 – July 2025)
 
Segment IV
Mission Street (Theresa Street to Trumbull Street/ Hwy 280 overpass)
(Approximately 9 months / June 2025 – January 2026)
 
 

Pavement and Sewer Renovation
Location
Mission Street between Geneva Avenue and Trumbull Street, Geneva Avenue between Mission Street and Prague Street
District
Start Fall, 2022
Completion Spring, 2026
Release Date
Friday, August 20, 2021
Budget
$20,000,000
Client
San Francisco Municipal Transportation Agency (SFMTA), San Francisco Public Utilities Commission (SFPUC)
Project Manager
Paul Barradas: (628) 271-2580
Project Team

- S.F. Public Works
- S.F. Municipal Transportation Agency (SFMTA)
- S.F. Public Utilities Commission (SFPUC)
- Bauman Landscape and Construction, Inc.
  (415) 447-4800 Office
  (415) 985-5641 After-Hours 

Contact
Alex Murillo: (628) 271-2244
Download Project Files
Full Project Rendering